- Project Completion Date – 2018
- Project Dollar Value – $5,351,646
- Project Description – T&T completed a full-depth replacement renovation of Taxiway G. This project included the demolition, pavement placement, joint sealant placement, pavement markings, shoulder work and related tasks to sustain Taxiway G. This project was designed to meet UFC criteria. Construction was completed in two phases to minimize impact to the active airfield. Components of the project included full depth replacement of 105,000 SF of existing asphalt overlay pavement with 18” Portland cement concrete on new base courses; Mill & overlay of 94,000 SF of existing asphalt pavement with 4” of new hot mix asphalt; Taxiway edge light replacement in paved shoulders and associated taxiway edge, centerline, and hold markings; Complex phasing to accommodate uninterrupted access for refueling missions, and private airport tenants that conduct commercial and military aircraft painting.